Taiwan's Climate Crisis and Net-Zero Transition: The Day the Nuclear Three Referendum Failed Was Just the Beginning of Physical Limits

August 23, 2025 Nuclear Three Extension Referendum: 4.34 million 'yes' votes, 74% approval, 29.53% turnout missed the threshold. The referendum failed; the next day, Lai Ching-te announced three principles. Seven months later, on March 27, 2026, Taipower submitted the extension application to the Nuclear Safety Commission. 98% energy import dependency, 9 trillion NTD net-zero target, geothermal target of 200 MW with only 7.4 MW built, offshore wind capacity ranked 7th globally, Onkalo ultimate repository, TerraPower Gen IV nuclear—this island's energy problem has never been a political one, but a question of physical limits.

30-Second Overview: On the evening of August 23, 2025, the results of the Nuclear Three extension referendum were announced: 4.34 million 'yes' votes, 74% approval, and a turnout of 29.53%, missing the threshold by 650,000 votes. The next day, President Lai Ching-te announced three principles: "Nuclear Safety Assurance, Nuclear Waste Solution, Social Consensus." Seven months later, on March 27, 2026, Taipower submitted the Nuclear Three re-operation application to the Nuclear Safety Commission, with the earliest restart expected in 202812. The referendum failed, yet Taipower is walking back toward nuclear power. This is the deepest contradiction of an island that relies on imports for 98% of its energy and has pledged to invest 9 trillion NTD to achieve net-zero by 20503. The government's geothermal target is 200 MW by 2030, but actual commercial operation by the end of 2025 is only 7.4 MW, a 27-fold gap; the Lanyu storage facility opened in 1982, holding 97,672 barrels of nuclear waste, with relocation deadlines missed four times45. Energy is a question of physical limits.

Nuclear Three Plant Exterior (Maanshan, Hengchun, Pingtung)

The Nuclear Three Plant (Maanshan Nuclear Power Plant) in Hengchun, Pingtung, is located on the Nanwan coastline. Unit 1 shut down on January 1, 2025, and Unit 2 on May 17, 2025. Image: M. Weitzel, CC BY-SA 3.0, via Wikimedia Commons

The Day of the Nuclear Three Referendum

On the evening of August 23, 2025, ballot counting was completed across all 22 counties and cities in Taiwan, and the results of the Nuclear Three extension referendum were announced: 4,342,206 'yes' votes, 1,511,693 'no' votes, with 74.17% approval. However, the turnout was only 29.53%. According to the Referendum Act, a threshold of one-quarter of the total number of voters (5,005,230 votes) was required. The 'yes' votes fell short by 658,317 votes1. More than twice as many people voted 'yes' than 'no', yet the referendum failed.

📝 Curator's Note: The common interpretation is "74% approval = clear public support for nuclear energy," but this reverses causality. The design of the Referendum Act was never about who had more votes; it required a mobilization threshold to prove that "enough people care." A 29.53% turnout means that over 70% of voters chose not to go to the polls. This is an even more awkward third signal: many people do not have strong enough opinions on energy issues to walk into a voting booth.

Two days later, on August 25, President Lai Ching-te held a press conference and gave a response: to restart nuclear power, three gates must be passed: "Nuclear Safety Assurance, Nuclear Waste Solution, Social Consensus"2. It sounds reasonable, but every one of these is a problem that has not been solved in 50 years.

Then came March 27, 2026. Taipower submitted the Nuclear Three re-operation application plan to the Nuclear Safety Commission, initiating the safety inspection procedure for Unit 1 after shutdown. The safety inspection schedule is expected to be about 18 months, with the earliest restart in 20281. This is a step backward.

From the referendum results to the submission for review, exactly seven months passed. Nothing changed in between: nuclear waste is still in Lanyu, the ultimate repository site has not been selected, and social consensus remains divided. But the administrative procedure moved. This is the question this article seeks to answer: When democratic voting rejects something but the administrative department advances it simultaneously, who is deciding Taiwan's energy policy?

Lanyu: 1982 to 2057

To understand the story of Nuclear Three, one must first understand the story of Lanyu.

In 1982, Taipower opened a low-level radioactive waste storage facility on the coastline south of Longmen in Lanyu. At the time, the Dawu residents were told it was a "fish cannery," a claim that later became the most frequently cited case of deception in Taiwan's environmental justice history6. In 1988, the Dawu people launched their first large-scale protest, using the traditional ritual of "exorcising evil spirits" to express their rejection of nuclear waste, marking the starting point of Taiwan's indigenous environmental movement.

Over the next 38 years, relocation promises were missed four times: the government promised relocation by 2002 in 1996; the first miss occurred in 2002; then misses occurred in 2016, 2019, and 2023. As of 2024, the Lanyu storage facility had accumulated 97,672 barrels of low-level radioactive waste. The Nuclear Subordinate Agency (NSA) requires Taipower to complete relocation by 2029, but the destination remains undefined4.

If 2029 is missed again (as widely expected in the industry), Lanyu's nuclear waste will be stored from 1982 to 2057, a total of 75 years. An island with a population of 4,000 bears the byproduct time of four nuclear power plants operating for the entire country, longer than the lifespan of most people in Taiwan.

⚠️ Controversial Viewpoint: Pro-nuclear advocates often say, "Nuclear waste is technically solvable; it's just political resistance." But the problem with nuclear waste has always been in the dimension of time. Lanyu has been storing waste since 1982, 44 years ago, and promises have never been fulfilled. In the most optimistic scenario, relocation happens in 2029; but what happens after "relocation from Lanyu"? The site selection for the ultimate repository is still stuck, and local resistance in Daren Township, Taitung County, remains unresolved. Technically feasible ≠ Politically feasible ≠ Ethically feasible. Lanyu is the concretization of this three-layer gap.

PanSci reports that spent nuclear fuel rods remain at high temperature and high radiation after reactor decommissioning and must be cooled in the plant's fuel pool for at least 5 years before they can be moved. The dry storage facility land issue for Nuclear One and Nuclear Two has been stuck for over 11 years; the New Taipei City Government refused to approve the dry storage facility, causing spent fuel rods to remain in the plant's fuel pool, exceeding the original design capacity78. "The biggest obstacle to nuclear power extension is the disposal of spent nuclear fuel," PanSci cites industry consensus, which is the most awkward background noise for the Nuclear Three re-operation application8.

The Physical Limits of Nuclear Waste

Shift the lens to Olkiluoto Island in southern Finland.

500 meters underground, in the granite layer, a 5-kilometer-long tunnel is dug. At the end of the tunnel lies Onkalo, humanity's first high-level radioactive waste ultimate repository to officially receive an operating license. In August 2024, Finland's nuclear safety authority, STUK, issued the license. This project, planned since the 1970s, took nearly half a century9.

Onkalo Underground Repository (Finland, Olkiluoto)

The entrance to Finland's Onkalo high-level radioactive waste ultimate repository, in the granite layer 500 meters underground, received an operating license in 2024. Image: kallerna, CC BY-SA 4.0, via Wikimedia Commons

Onkalo's design goal is to isolate nuclear waste for more than 100,000 years. How exaggerated is this timescale? Human civilization is about 10,000 years old; the oldest pyramids are 4,500 years old; 100,000 years ago, our ancestors had not yet left Africa10.

💡 Did You Know? The timescale for isolating nuclear waste in an ultimate repository is so long that it reaches the "end of human memory." The Onkalo design team spent years discussing one question: How to make humans 100,000 years from now know "Do not dig here"? Because by then, no existing language, symbol, government, or religion will remain. The final solution uses a nuclear waste warning symbol with multilingual warnings, but designers admit this is only a "message for the next 1,000 years." What happens after 1,000 years? No one knows the answer.

What about Taiwan's ultimate repository? The candidate site for the low-level nuclear waste ultimate repository is Daren Township, Taitung County, but the site selection process is stuck due to local political resistance11. The site selection process for the high-level nuclear waste ultimate repository has not even started. Finland took 50 years to reach the trial operation stage; Taiwan has zero years.

PanSci also mentions another "physical limit solution" that was seriously discussed: space disposal of nuclear waste. "The idea of space disposal of nuclear waste is physically feasible, but requires very stable and reliable rockets; otherwise, if a launch fails, the radiation pollution caused to Earth will be incalculable"12. SpaceX's Falcon 9 failure rate is about 1%, meaning that for every 100 launches, one will explode high-level radioactive nuclear waste into the atmosphere. Physically feasible, but physically also not feasible.

This is the physical limit behind the four words "Nuclear Waste Solution." Its timescale is longer than that of the entire human civilization.

Hydrogen Rainbow: Green, Blue, Gray, White, Gold

If nuclear power is too heavy, can we go around it?

Over the past five years, hydrogen energy has been seen as the next wave of energy transition. The problem is that hydrogen itself is an energy carrier rather than an energy source: other energy must first be used to "produce" hydrogen, which is then used for power generation or as fuel. Where it comes from determines whether it is truly "clean."

PanSci categorizes hydrogen by production method: "Hydrogen color codes correspond to different production methods: Gray Hydrogen (Natural Gas SMR, emits CO₂), Blue Hydrogen (Gray Hydrogen + CCS), Green Hydrogen (Renewable Electricity Electrolysis), Blue-Green Hydrogen (Methane Pyrolysis, solid carbon capture, no CO₂ emission). From a carbon emission perspective, Green Hydrogen is ideal but has the highest cost"13.

Hydrogen Color Production Method Carbon Emission Cost Taiwan Status
Gray Hydrogen Natural Gas Steam Methane Reforming (SMR) High (Emits CO₂) Low Most common in industry
Blue Hydrogen Gray Hydrogen + Carbon Capture and Storage (CCS) Medium (Reduced after CCS) Medium-High No commercial operation
Green Hydrogen Renewable Electricity Electrolysis Zero High CPC Planning
Blue-Green Hydrogen Methane Pyrolysis (Decarbonization Combustion) Zero (Produces Solid Carbon) Medium Hsingda Power Plant Trial
White/Gold Hydrogen Naturally Formed Underground Zero (No Production Needed) To Be Explored None

Taiwan's hydrogen trial point is at Hsingda Power Plant in Kaohsiung. Taipower and the Academia Sinica are collaborating to test "Decarbonization Combustion" technology: decomposing natural gas (methane) into hydrogen and solid carbon at high temperatures, a process that does not produce carbon dioxide, and the solid carbon can be used as an industrial raw material13. The attractiveness of this technology lies in the fact that it can use existing natural gas infrastructure, avoiding the need to tear down and rebuild the entire energy system.

But hydrogen has its own physical limits. "Although hydrogen is a clean energy, its effect as a greenhouse gas is 11.6 times that of carbon dioxide (GWP100). If it leaks during production, transportation, or use, it will exacerbate warming"14. The hydrogen molecule is the smallest molecule in the universe, and its leakage rate is inherently high. This is a physical limit of materials science, not something that can be fully overcome by engineering efforts.

There is also a newer role: White/Gold Hydrogen. A 2023 study by the U.S. Geological Survey (USGS) estimated that the reserves of naturally formed hydrogen gas underground due to crustal movement may reach "tens of billions of tons," sufficient to provide energy for humanity for hundreds of years1415. France and Mali already have commercial exploration. Taiwan's plate boundaries are active, theoretically holding potential, but currently, there are no exploration plans. This is the energy option furthest from theory.

📝 Curator's Note: The core takeaway from the hydrogen rainbow classification for readers is to always ask "Where does the energy come from?" behind the term "clean energy." Green hydrogen is only cost-effective when renewable electricity is in excess and has nowhere to sell; this situation has not yet arrived in Taiwan. Until then, hydrogen is actually a showroom for another fossil fuel.

Geothermal Taiwan: 33 GW Potential vs. 7.4 MW Reality

If hydrogen is a "carrier dispute," geothermal is a "depth dispute."

Taiwan should naturally be a geothermal powerhouse. Located at the junction of the Eurasian Plate and the Philippine Sea Plate, volcanoes, hot springs, and earthquake zones form a natural geothermal resource reservoir. In 1981, the Qingshui Geothermal Power Plant in Yilan built a 3 MW experimental unit, Taiwan's first geothermal power plant. However, due to technical issues such as wellbore scaling and acid corrosion, it closed in 1993.

For the next 30 years, geothermal in Taiwan fell into silence. Until 2020, the privately invested Qingshui Geothermal 4.2 MW unit restarted commercial operation, bringing geothermal back into public discussion. In 2024, the Yilan Tufang Geothermal 5.4 MW project broke ground, expected to start in early 2026. By the end of 2025, the total commercial capacity of geothermal power in Taiwan will be 7.4 MW16.

What is the government's official target? 200 MW by 2030, 6 GW (6,000 MW) by 2050. From 7.4 MW to 200 MW is a 27-fold difference; to 6 GW, an 810-fold difference. This is a timeline of 5 years and 25 years.

PanSci cites a National Taiwan University study stating that "Taiwan's geothermal resources are widely distributed. According to a National Taiwan University study, the potential power generation of deep geothermal (depth below 5 km) reaches 33,640 MW, equivalent to about 12 Nuclear Four plants"17. But this is only a theoretical value. Developing deep geothermal requires Enhanced Geothermal System (EGS) technology, which must drill wells several kilometers underground and inject water artificially to create a heat exchange layer. Currently, there are only a few demonstration projects globally, and the technology is not yet commercialized.

And "Taiwan's shallow geothermal (depth within 3 km) development potential is estimated to be no more than 1,000 MW. Currently, several experimental projects are underway in Yilan Qingshui and Taipei Datun Mountain areas"17. Even if shallow geothermal is fully opened, it would only provide about 3% of Taiwan's total electricity demand.

Geothermal's advantage is stability. "Geothermal's advantage is that it is not affected by weather like wind or solar power; it is a baseload power source that generates electricity stably 24 hours a day, giving it unique value in the energy mix"18. There are not many renewable energies that can replace nuclear baseload functions; geothermal is one of them, provided it can actually be built.

⚠️ Controversial Viewpoint: The slow development of geothermal in Taiwan is often attributed to "immature technology." But PanSci's interviews with the industry yield a different conclusion: the real bottleneck is underground uncertainty + difficulty in loans. Before drilling a geothermal well, no one can guarantee water will flow, how hot it will be, or how long it will last. Banks do not lend; developers dare not invest. Japan and New Zealand face similar dilemmas, but both have government-led funds to share risks. Taiwan's geothermal developers currently use the solar PV financing model: solar PV generates electricity once installed; geothermal does not. Copying the financing structure guarantees a deadlock.

Public Television's Our Island produced a two-part series "Using Heat for Power" in March 2023, following the national team into Datun Mountain, Yilan, and Taitung tribes, comprehensively filming the two aspects of "geothermal exploration's observation, listening, questioning, and pulse-taking" and "tribal geothermal power generation":

Public Television's Our Island Official Channel: Episode 1195 "Geothermal Exploration National Team Mobilized" (2023-03-06). In Datun Mountain and Yilan Jiaoxi, follow the exploration teams from the Ministry of Economic Affairs' Geological Survey Bureau, Taipower's General Research Institute, and the Industrial Technology Research Institute to see how "geothermal mushrooms" are pieced together from three clues: seismic waves, rock samples, and well temperature gradients. How much heat is in Taiwan's underground only becomes concrete from here.

Public Television's Our Island Official Channel: Episode 1196 "Geothermal Power Generation in Tribes" (2023-03-13). Presenting both levels of "energy transition vs. local justice"—Yilan Lizhi, Taitung Hongye, Chiayi Zhonglun. Geothermal development reaches which tribal negotiation line? Technical issues are one thing; sociologically, whether it can enter is a completely different matter.

Ocean Energy: The Trial Stage of 9.4 GW from the Kuroshio

After the underground, there is the sea.

The Kuroshio current off eastern Taiwan is one of the world's strongest currents. Flow speed 1.5-2.5 meters/second, width about 100 km, flowing north year-round. Theoretically, this is a never-ending energy river. The Academia Sinica completed the offshore testing of a 100 kW experimental unit in 2021, a milestone in Taiwan's ocean energy development19.

PanSci cites the Academia Sinica estimate: "Taiwan's surrounding waters have huge renewable energy potential. The theoretical potential of ocean energy (including current energy, wave energy, and thermal energy) is estimated at 9.4 GW. The Kuroshio flowing past Taiwan's east coast is the most promising current energy source"19.

Another direction is OTEC (Ocean Thermal Energy Conversion): using the temperature difference between surface warm water (25-28°C) and deep cold water (5°C) to drive generators. Taiwan's eastern sea area has a large depth drop and is considered an ideal location for OTEC. "Taiwan's eastern sea area has a large depth drop, theoretically an ideal location for OTEC development, but it is still in the experimental stage"20.

But ocean energy's physical limits are encountered earlier than geothermal: the durability of marine engineering. Typhoons, salt corrosion, biofouling, deep-water maintenance—each is a century-level engineering challenge. Internationally, OTEC has no commercial power plants operating; the global leading case for Kuroshio power generation is Japan's Okinawa 100 kW demonstration. Taiwan's 100 kW trial is just the starting point. From here to commercialization, international experience shows it takes 15-20 years.

Fourth-Generation Nuclear SMR: Bill Gates' Bet

If we go back to the path of nuclear power, will fourth-generation nuclear energy be the answer?

PanSci reports: "The biggest difference between the Natrium reactor and traditional nuclear power plants is its coolant. Traditional nuclear reactors use water as a coolant, while Natrium uses liquid metal sodium. Sodium has a high boiling point and can operate at higher temperatures, improving reaction efficiency; sodium's thermal conductivity is 100 times that of water"21.

This is the sodium-cooled fast neutron reactor promoted by TerraPower, founded by Bill Gates. In April 2026, TerraPower's Natrium project officially broke ground in Kemmerer, Wyoming, expected to be completed in 203022, one year later than originally scheduled, but still a key milestone in the commercialization of fourth-generation nuclear energy.

The selling point of fourth-generation nuclear energy is "Small Modular Reactors" (SMR): power generation capacity drops from the traditional 1000 MW level to 100-300 MW, can be prefabricated in factories and assembled on-site, theoretically reducing costs and shortening construction time.

But physical limits still exist. PanSci points out two key risks:

"Fast neutron reactors require high-concentration uranium fuel, and breeding reactions produce Plutonium-239, an important raw material for nuclear weapons. Therefore, how to manage nuclear materials and prevent nuclear proliferation becomes a problem that fast neutron reactors must face"23.

"The construction of the Natrium reactor marks a major advance in fourth-generation nuclear power plant technology, but its development also comes with significant challenges"24. Liquid sodium reacts violently and is flammable when it contacts water; reactor operation and maintenance have extremely high requirements for materials science, and there are currently no large-scale commercial operation safety data.

Does Taiwan have an SMR plan? Currently, there are no official plans. Even if evaluation starts now, from site selection, environmental impact assessment, safety review to commercial operation, international experience shows it takes 15-20 years. That is to say, fourth-generation nuclear energy is not the answer for 2050 net-zero; the most optimistic scenario is online by 2045-2050.

📝 Curator's Note: Fourth-generation nuclear energy is often treated in international public opinion as "nuclear energy of the future," thus becoming "a good excuse to delay current energy transition": since better technology will be available in 15 years, why rush now? This is the most dangerous confusion in the physical limits question. The engineering bottleneck of renewable energy is "not enough built yet"; the bottleneck of fourth-generation nuclear energy is "safety and non-proliferation data for commercial operation not yet accumulated enough." The two timelines cannot replace each other. Missing the 2030 renewable energy construction window, the 2045 SMR cannot save the climate bill.

Offshore Wind: The Leading Piece in Asia

Pull the lens back to what is already happening.

Hai Neng Offshore Wind Farm off Miaoli

The Hai Neng Offshore Wind Farm (Formosa 1) off Miaoli, commercial operation started in 2019, is Taiwan's first large-scale offshore wind farm. Image: Ministry of Economic Affairs, Attribution, via Wikimedia Commons

The Taiwan Strait is one of the world's best wind farm sites. "Due to topographical factors, the Taiwan Strait forms a 'pipe effect,' causing wind speeds in the strait to be much higher than surrounding waters, making Taiwan one of the most potential locations for offshore wind development globally"25. Winter Northeast Monsoons are squeezed into the strait by the Central Mountain Range and Fujian hills, with average wind speeds of 10-12 meters/second. This geographical fact makes offshore wind the core bet of energy transition.

From almost zero in 2016 to a cumulative installed capacity of about 4.5 GW by March 20263, Taiwan's offshore wind expansion speed ranks among the top in Asia. Ørsted from Denmark completed the construction of 920 MW for the Da Changhua Southwest Phase II and Northwest Wind Farms off Changhua26. The third phase block development starting in 2026 has an allocated capacity of 3.6 GW, targeting completion and grid connection by 2030-20313.

The government's blueprint is larger: 13 GW offshore wind by 2030, challenging 55 GW by 2050.

But offshore wind turbines bring not only power but also conflict. In February 2022, over a hundred Changhua fishermen went north to the Executive Yuan to protest, accusing the government of "eliminating fishermen" for wind power27. The navigation ban zones set by offshore wind farms blocked the sea areas where they had operated for generations. In May 2025, the court ruled the navigation restrictions illegal, the first time a court in Taiwan challenged the spatial governance of offshore wind28.

Solar PV takes another path. Solar PV installed capacity reached 14,281 MW in 2024, accounting for 68% of total renewable energy, with 14.9 billion kWh generated29. Roof-mounted, ground-mounted, water-surface-mounted, agrivoltaics—diverse installation models make solar the mainstay of renewable energy. But the agrivoltaics policy has triggered questions of "fake farming, real power generation," forcing the Ministry of Agriculture to strengthen inspections. On an island with only 790,000 hectares of arable land, the use of every piece of land is a political issue.

Solar Panels on Xihu Service Area Roof

Solar panels on the roof of Xihu Service Area. Taiwan's solar PV installed capacity reached 14,281 MW in 2024, accounting for 68% of renewables. Image: lienyuan lee, CC BY 3.0, via Wikimedia Commons

Wind and light are the fastest piece of the puzzle in Taiwan's energy transition, but are inherently intermittent: no power when the sun sets, no power when the wind stops. This is also the most common argument used by pro-nuclear advocates in the Nuclear Three extension discussion: "Renewable energy is unstable; it needs baseload." The question returns to the geothermal section: if baseload renewable energy is not built fast enough, the 27-fold target gap is the political support for Nuclear Three's 2028 restart timeline.

The Afternoon of May 13

At 2:37 PM on May 13, 2021, at the Lu-bei Extra High Voltage Substation of Hsingda Power Plant in Kaohsiung, an operator opened switch 3541; he was supposed to open 354230.

This human error triggered a busbar ground fault, tripping four units and instantly losing 2.2 GW of power generation capacity. Starting at 3 PM, Taiwan implemented six rounds of regional power rationing, each lasting 50 minutes, affecting about 4 million households. To make matters worse, solar power generation decreased with sunset, and drought reduced hydropower. It was not until 7 PM when coal units came back online, and 8 PM when power was fully restored.

Four days later, on May 17, Hsingda Unit 1 failed again, bringing a second round of blackouts. The two events combined affected over 5.62 million households30.

May 13 and May 17 exposed how fragile a transitioning power system is, far beyond the level of human negligence. The government's solution is energy storage: planning 1.5 GW of battery storage by 2025, expanding to 8.6 GW by 2030. But storage costs remain high, and the technology is still maturing.

This is the most honest side of energy transition: the old system is no longer sufficient, and the new system is not yet ready. Whether the Nuclear Three extension referendum passes or not cannot change this reality; it can only delay or accelerate the time of facing it.

Giving Carbon a Price

On August 7, 2023, the Taiwan Carbon Exchange was listed in the Asia New Bay Area of Kaohsiung, with an initial paid-in capital of 1 billion NTD and a planned capital of 1.5 billion NTD; the Stock Exchange contributed 600 million NTD, and the National Development Fund contributed 400 million NTD31. On December 22, 2023, the first batch of international carbon credit transactions was completed: 45 enterprises purchased about 88,500 tons of CO₂ equivalent international carbon credits for over $800,00031.

In 2025, the domestic carbon fee system officially went online, and Taiwan entered the "Year of Carbon Pricing"32. Formosa Plastics' energy efficiency improvement project was listed at 3,000 NTD per ton; Hanbao Agriculture's biogas power generation project was priced at 3,000 to 4,000 NTD. But the market is still exploring: trading volume is low, and enterprises generally believe domestic carbon credit prices are too high.

At the same time, tech giants like TSMC and Foxconn are already seizing the beachhead in another battlefield. Under the RE100 initiative, these enterprises have committed to using 100% renewable energy. TSMC plans to reach net-zero emissions by 2050. When international customers make green power a supply chain threshold, green power supply becomes an industrial survival issue, not just an environmental issue.

The EU Carbon Border Adjustment Mechanism (CBAM) will enter the formal system in 2026, increasing the carbon cost and reporting pressure for high-carbon products such as steel, cement, aluminum, fertilizers, electricity, and hydrogen exported to Europe33. Taiwan's manufacturing industry is dominated by energy-intensive industries; the four major industries of steel, petrochemicals, cement, and paper account for 60% of industrial emissions. This is another physical limit, a timeline set by international trade structure for Taiwan.

In the 2024 National Day Speech, Lai Ching-te announced the launch of "Secondary Energy Transition," covering three directions: diversified green energy, deep energy saving, and advanced energy storage34. But renewable energy share in 2025 remained significantly below the original 20% target; depending on statistical口径, it was about 12.7% to 13.1%35. The Ministry of Economic Affairs has now changed the estimate to say it can reach 20% from November 2026, and about 30% by 2030.

Algae Reef, Dawu, Meigong: Fault Lines of Environmental Justice

Every energy path has its own opponents, and every opponent has their own history.

Taoyuan Algae Reef. The 2021 "Save Algae Reef Referendum" (Case 20) opposed Taipower building the Third Natural Gas Receiving Terminal on the Datan coast, aiming to protect the world's largest columnar algae reef terrain. The referendum failed, and the Three-Interface compromise plan went online: port area pushed out, avoiding high-density algae reef areas. Algae reef scholars still believe the EIA was insufficient, but the EIA Committee passed the review in 2023. The controversy has not subsided; this is the physical/ecological intersection of "building natural gas for carbon reduction, moving algae reefs for natural gas."

Lanyu Dawu People. From 1982 to 2026, 44 years of nuclear waste storage history is Taiwan's longest wound of environmental justice. Dawu people continued to protest relocation misses in 2024; in May of that year, the NSA announced it required Taipower to complete relocation by 2029. But where to relocate remains unanswered4.

Meigong Anti-Dam. The Meigong Anti-Dam Movement of the 1990s,凝聚ing resistance with "Meigong Yellow Butterfly Festival" and "Hakka Spirit," ultimately forced the dam project to retreat, a classic of Taiwan's community-based environmental movement. Reading Meigong today, one finds its spirit still influencing other energy battlefields: every wind turbine, every solar panel, every transmission line entering a locality encounters the response "We oppose the transition costs being borne by us, not opposing energy transition itself."

📝 Curator's Note: Common environmental justice discussions often stop at "balancing development and environmental protection," but this framing flattens the problem. The true commonality of Lanyu, Algae Reef, and Meigong is: they are all post-1980s decision legacies, paid for by 1990-2020 social movements. Energy transition will produce many new "Lanyus" and "Algae Reefs" before 2050 (Changhua fishermen for offshore wind, Yilan indigenous for geothermal, Tainan salt fields for solar). The real question is "Can we avoid repeating the 1982 decision-making model?"

For detailed environmental justice historical context, see Taiwan Environmental Movement History and Taiwan Marine Pollution Governance and Conservation Challenges.

9 Trillion NTD and Physical Limits

Putting all energy on the same table, the gap in physical limits becomes visible.

Energy Taiwan Theoretical Potential 2025 Status Government Target / Timeline Main Physical Limit
Offshore Wind One of the best globally 4.5 GW 13 GW by 2030, 55 GW by 2050 Marine Engineering / Fishery Conflict
Solar PV Rooftop + Agrivoltaics 14.3 GW 31 GW by 2030 Land Acquisition / Intermittency
Geothermal (Shallow) ≤ 1,000 MW 7.4 MW 200 MW by 2030, 6 GW by 2050 Underground Uncertainty / Financing
Geothermal (Deep EGS) 33,640 MW (Theoretical) Lab Stage 2040+ EGS Technology Not Commercialized
Ocean Energy 9.4 GW (Theoretical) 100 kW Trial 2030+ Marine Engineering Durability
Hydrogen (Green) Requires Large Renewable Power Hsingda Trial 2030+ Electrolysis Cost / Leakage GWP
Nuclear Three Extension 1,902 MW 2025 Shutdown Earliest Restart 2028 Nuclear Waste / Safety Review
Fourth-Gen Nuclear SMR No Local Plan US 2030 Trial 2045+ Sodium Safety / Nuclear Proliferation

This table answers one question: Without nuclear energy, can Taiwan achieve 2050 net-zero?

Technically, yes. The NDF's roadmap lists 12 key strategies, estimating 9 trillion NTD in investment36. But it requires offshore wind, solar PV, geothermal, ocean energy, hydrogen, and storage to simultaneously achieve their respective targets. And currently, geothermal is 27 times short, ocean energy is still at kW level, hydrogen is still in trial, and storage costs are still high.

Every physical limit is time.

In Hsu Hsiung-hsiung's model, Taiwan after 2060 will have no winter37. In coastal risk assessments, western low-lying areas are facing higher sea-level rise and storm surge pressure38. From 1911 to 2020, Taiwan's annual average temperature has risen 1.6°C, almost one and a half times the global average (1.1°C) for the same period37.

An Island Warming by One and a Half Degrees

In the summer of 2017, Hsu Hsiung-hsiung of the Academia Sinica's Center for Environmental Change Research stared at data on his screen and made a prediction that colleagues were reluctant to say publicly: if emission trends continue, Taiwan's winter might disappear completely after 206037. Winter days drop to zero, summer stretches to seven months.

This is not science fiction. Days above 35°C in Taipei have surged from 3 days a year in the 1960s to 15 days in the last decade39. The south is more severe; Tainan and Kaohsiung annual high-temperature days have exceeded 30 days.

In the same building, Wang Chung-ho of the Institute of Earth Sciences is calculating another set of numbers. His conclusion is equally unsettling: the rate of sea-level rise around Taiwan is twice the global average38. Multiple simulations indicate that sea-level rise and storm surges will increase the risk of inundation for Taiwan's western low-lying coastal areas; among the six municipalities, the exposed population and land area in New Taipei, Tainan, and Kaohsiung are particularly concerning.

Rain's temperament has also changed. Taiwan's total rainfall has not significantly decreased, but it doesn't fall when it should, and falls heavily when it does. Spring rainfall has sharply decreased, dry seasons are drier. In 2021, Taiwan suffered its most severe drought in 56 years, reservoir storage rates hit historical lows, and TSMC once sent water trucks to factories for water40. In May of the same year, two major blackouts struck the island in succession.

Days with over 200 mm of rainfall per day have increased from an annual average of 5 days in the 1960s to 8 days in recent years. The 2009 Morakot Typhoon created a cumulative rainfall record of 2,884 mm at Alishan41; the rain falling in three days was equivalent to Taipei's entire annual rainfall. In that typhoon, in the early morning, the village of Hsiao-lin in Jiashan, Kaohsiung was buried by collapsing earth and rocks from Xiandu Mountain, killing 491 people42.

"Every chair represents one family member." Survivor Wang Min-liang later said to visitors in the Hsiao-lin Memorial Park like this. He established the Sunlight Hsiao-lin Community, touring the island with the tribe's Grand Manzu Dance Troupe. (Quote from Public Television's Our Island)

The 2024 National Climate Change Science Report hosted by Hsu Hsiung-hsiung points out: extreme rainfall events that currently occur once every 50 years may occur once every 10 years in the future43. Yunlin, Tainan, and Keelung are the areas with the highest coastal flood risk.

For an island of 23 million people, Taiwan's carbon emissions are disproportionately large: measured by fossil fuel CO₂ emissions, annual emissions are about 280 million tons, per capita about 11.7 tons, ranking in the global top tier; depending on different databases and statistical口径, the ranking is about 20th globally44. Emissions are highly concentrated in energy use and power supply, with the energy sector having the highest proportion; the power generation structure remains the core of carbon reduction pressure. The root of the problem lies in the power generation structure: in Taiwan's 2024 power generation structure, gas is about 42.4%, coal about 39.3%, gas has surpassed coal for the first time; renewables are about 11.6%, nuclear about 4.2%35. This is an energy system still highly dependent on fossil fuels, and Taiwan relies on imports for 98% of its energy. Energy security and climate crisis are the same question.

Parallelism of Democracy and Physics

The evening of August 23, 2025, the Nuclear Three referendum pushed all the contradictions of this question onto the ballot screen.

74% approval, 29.53% turnout, threshold not met, Taipower submission in March 2026, earliest restart 2028. Simultaneously: Lanyu 97,672 barrels, Finland Onkalo took 50 years, geothermal 27 times short, ocean energy still at 100 kW, fourth-generation nuclear energy until 2045. Every number asks: Can the speed of democracy keep up with the speed of physics?

Democratic Timeline Physical Timeline
2025/08/23 Referendum Results Lanyu Opened 1982, Still There 2057
2025/08/25 Three Principles Press Conference Nuclear Waste Isolation 100,000 Years
2026/03/27 Taipower Submission Ultimate Repository Finland Took 50 Years
2028 Earliest Restart Geothermal 27 Times Short
2050 Net-Zero Target Ocean Energy Still 100 kW Trial

Whether 9 trillion NTD can buy a different future, no one knows. But the consequences of not spending this money, we are already seeing: Hsu Hsiung-hsiung's 2060 no winter, Morakot's 2,884 mm, May 13 rolling blackouts, Algae Reef Referendum撕裂, Lanyu's 44-year wait.

PanSci reports citing industry consensus: "The fastest progress on global ultimate repositories is Finland's Onkalo project, which received an operating license in August 2024. This project started planning in the 1970s and took nearly half a century to reach the trial operation stage"9. Taiwan's ultimate repository has not even selected a site. Even if Nuclear Three restarts in 2028, every new fuel rod produced during the restart period must find a place to be stored.

Lanyu's 97,672 barrels will not disappear because the referendum passed or failed. They are there now, likely still there in 2029, and still there in 2057 (if relocation is missed again).

On August 23, 2025, the referendum failed. On March 27, 2026, Taipower still submitted the application. Between these two dates, the physical limits have not changed once. What has changed is whether we are willing to admit that this island, relying on imports for 98% of its energy, is queuing to face all the physical limits no one wants to face.


Further Reading:

References

Image Sources

  1. Central Election Commission: 2025 August 23 National Referendum Results Announcement — ; CNA: Nuclear Three Extension Referendum 4.34 Million 'Yes' Votes Missed 1/4 Threshold, Failed — ; Taipower: Nuclear Three Re-operation Plan Submitted to Nuclear Safety Commission Review Explanation (2026/03/27) — 2025/08/23 Nuclear Three Extension Referendum: 'Yes' votes 4,342,206 (74.17%), 'No' votes 1,511,693, turnout 29.53%, missed Referendum Act threshold of 1/4 of total voters (5,005,230 votes), referendum failed. Taipower submitted Nuclear Three re-operation plan application to Nuclear Safety Commission on March 27, 2026, expected safety inspection schedule about 18 months, earliest restart 2028.
  2. CNA: Lai Ching-te Nuclear Three Referendum Post-Talk Proposes Nuclear Safety, Nuclear Waste, Social Consensus Three Principles — President Lai Ching-te issued formal response on August 25, 2025 regarding Nuclear Three extension referendum results, proposing "Three Principles" for future nuclear restart: Nuclear Safety Assurance, Nuclear Waste Solution, Social Consensus, and instructed Ministry of Economic Affairs and Nuclear Safety Commission to start safety inspection procedure evaluation.
  3. Ministry of Economic Affairs Energy Bureau: Offshore Wind Block Development Phase 3 Selection Mechanism Announcement Gunshot Starts — Ministry of Economic Affairs announced on March 27, 2026, stating that as of March 26, 2026, Taiwan's cumulative offshore wind installed capacity is about 4.5GW, Phase 3 allocated capacity is 3.6GW, targeting completion and grid connection by 2030-2031.
  4. Nuclear Subordinate Agency: Lanyu Storage Facility Storage Volume Announcement (2024) — NSA official announcement, as of 2024 Lanyu low-level radioactive waste storage facility accumulated storage 97,672 barrels, since 1982 opening experienced 1996, 2002, 2016, 2019, 2023 multiple relocation promise misses, NSA requires Taipower to complete relocation by 2029. Content Curation Partner per MOU 2026-05-05.
  5. Ministry of Economic Affairs Energy Bureau: Geothermal Power Generation Target and Commercial Capacity (2025) — Government geothermal power generation policy target: 200 MW by 2030, 6 GW (6,000 MW) by 2050; as of end of 2025 Taiwan geothermal commercial capacity about 7.4 MW, mainly Yilan Qingshui Geothermal 4.2 MW and some small units, 27 times short of 2030 target.
  6. Wikipedia: Lanyu Storage Facility — Before Lanyu Storage Facility opened in 1982, Taipower told Dawu residents it was building a "fish cannery," failing to fully inform the nature of nuclear waste storage; 1988 Dawu people launched first "Exorcise Evil Spirits" protest action, marking the starting point of Taiwan's indigenous environmental movement.
  7. PanSci: Nuclear Two Exit, Nuclear Waste Still to Be Stored for 20 Years — Content Curation Partner per MOU 2026-05-05. Nuclear Two Plant officially decommissioned at end of 2023, but nuclear fuel rods remain at high temperature and high radiation after reactor decommissioning, must be cooled in plant fuel pool for at least 5 years before they can be moved; Daren Township, Taitung County is the candidate site for low-level nuclear waste ultimate repository, site selection process stuck due to local political resistance.
  8. PanSci: What Is the Real Problem of Nuclear Power Extension — Content Curation Partner per MOU 2026-05-05. Nuclear power plant dry storage facility land issue stuck for over 11 years, New Taipei City Government refused to approve dry storage facility, causing spent fuel rods of Nuclear One and Nuclear Two to remain in plant fuel pool and exceed original design capacity; biggest obstacle to nuclear extension is the disposal of spent nuclear fuel.
  9. PanSci: Since Nuclear Waste Has Nowhere to Go, Is There Another Method — Content Curation Partner per MOU 2026-05-05. Fastest progress on global ultimate repositories is Finland's Onkalo project, received operating license in August 2024, started planning in 1970s, took nearly half a century to reach trial operation stage; ultimate repository needs to isolate waste for over 100,000 years, this timescale far exceeds the existence time of human civilization.
  10. Posiva Oy: Onkalo Ultimate Repository Design Introduction — Finland Posiva Company operated Onkalo repository official explanation, design goal is to isolate high-level radioactive nuclear waste for at least 100,000 years, including multi-barrier system (copper shell + bentonite + granite layer) and long-term memory warning system design.
  11. Taitung County Daren Township Office: Low-Level Radioactive Waste Ultimate Repository Issue — Daren Township, Taitung County is one of two candidate sites for low-level nuclear waste ultimate repository (the other is Kinmen Wuchu), local public opinion divided, indigenous tribe opposition voices strong, site selection referendum has not successfully held.
  12. PanSci: Nuclear Waste Space Disposal Feasibility Analysis — Content Curation Partner per MOU 2026-05-05. Nuclear waste space disposal is physically feasible but requires very stable and reliable rockets, if launch fails radiation pollution caused to Earth will be incalculable; with existing rocket failure rate, about 1 in 100 launches has risk, not meeting engineering practice needs.
  13. PanSci: Improved Natural Gas Power Generation Technology Does Not Produce Carbon Dioxide? Gray Hydrogen, Blue Hydrogen, Green Hydrogen — Content Curation Partner per MOU 2026-05-05. Hydrogen color codes correspond to different production methods: Gray Hydrogen (Natural Gas SMR emits CO₂), Blue Hydrogen (Gray Hydrogen + CCS), Green Hydrogen (Renewable Electricity Electrolysis), Blue-Green Hydrogen (Methane Pyrolysis solid carbon capture no CO₂ emission); Taipower and Academia Sinica have collaborated on Hsingda Power Plant for decarbonization combustion technology testing.
  14. PanSci: Musk Disdains; Bill Gates Treasures! Hydrogen Energy — Content Curation Partner per MOU 2026-05-05. Besides Green Hydrogen, emerging White/Gold Hydrogen is naturally formed underground hydrogen, USGS estimates reserves may reach tens of billions of tons; but hydrogen's GWP100 is 11.6 times that of carbon dioxide, leakage will exacerbate warming problem (academic community still has 7-37 range controversy on GWP numbers).
  15. USGS: Geological Hydrogen — A New Energy Frontier (2023) — U.S. Geological Survey 2023 Geological Hydrogen Research Report, estimating global underground natural hydrogen reserves may reach tens of billions of tons, sufficient to provide energy for humanity for hundreds of years; France, Mali have commercial exploration cases, Taiwan plate boundaries active but currently no exploration plans.
  16. CNA: Yilan Tufang Geothermal Power Plant Construction Starts, Expected 2026 Launch — 2024 Yilan County Tufang Geothermal Power Plant 5.4 MW unit construction started, expected to launch in early 2026, Taiwan's second MW-scale commercial geothermal power plant; as of end of 2025 Taiwan geothermal commercial about 7.4 MW, including Qingshui Geothermal 4.2 MW and other small units.
  17. PanSci: Is Taiwan Developing Geothermal Power Generation Feasible (Part 1) — Content Curation Partner per MOU 2026-05-05. According to National Taiwan University study, deep geothermal (depth below 5 km) potential power generation reaches 33,640 MW, equivalent to about 12 Nuclear Four plants, but development requires EGS Enhanced Geothermal System technology still in R&D stage; shallow geothermal (depth within 3 km) potential estimated no more than 1,000 MW.
  18. PanSci: Geothermal Advantages and Taiwan Field Application — Content Curation Partner per MOU 2026-05-05. Geothermal is not affected by weather, is a 24-hour stable power generation baseload power source, has unique value in energy mix; but underground uncertainty leads to financing difficulties, is the fundamental bottleneck of Taiwan's geothermal development slow.
  19. PanSci: "Protecting Mountain God" Higher, Power Pressure Greater: Taiwan Ocean Energy Is Solution — Content Curation Partner per MOU 2026-05-05. Taiwan surrounding waters ocean energy (current, wave, thermal) theoretical potential reaches 9.4 GW; Kuroshio flowing past Taiwan's east coast is most promising current energy source, Academia Sinica completed 100 kW trial unit testing in 2021.
  20. PanSci: Ocean Thermal Energy Conversion (OTEC) Taiwan Possibility — Content Curation Partner per MOU 2026-05-05. OTEC uses temperature difference between surface warm water (25-28°C) and deep cold water (5°C) for power generation, Taiwan's eastern sea area large depth drop, theoretically ideal location, but still in experimental stage, no commercial operation power plants globally.
  21. PanSci: Bill Gates' Fourth-Generation Nuclear Power Plant Finally Starts Construction — Content Curation Partner per MOU 2026-05-05. Natrium reactor biggest difference from traditional nuclear power plants is coolant: traditional uses water, Natrium uses liquid metal sodium; sodium high boiling point, can operate at higher temperatures improving reaction efficiency, thermal conductivity 100 times water.
  22. TechOrange: TerraPower Natrium Project 2026 Breaks Ground in Wyoming — TerraPower's Natrium fourth-generation nuclear power plant project officially breaks ground in Kemmerer, Wyoming in April 2026, slightly delayed from original plan, expected completion 2030, global fourth-generation sodium-cooled fast neutron reactor commercialization key milestone.
  23. PanSci: Fourth-Generation Nuclear Energy Nuclear Proliferation Risk — Content Curation Partner per MOU 2026-05-05. Fast neutron reactors require high-concentration uranium fuel, breeding reactions produce Plutonium-239, important raw material for nuclear weapons; how to manage nuclear materials, prevent nuclear proliferation, is problem fast neutron reactors must face.
  24. PanSci: Natrium Reactor Safety Challenges — Content Curation Partner per MOU 2026-05-05. Natrium reactor construction marks fourth-generation nuclear power plant technology progress, but development comes with major challenges; liquid sodium reacts violently and is flammable when contacting water, reactor operation and maintenance extremely high requirements for materials science, currently lacks large-scale commercial operation safety data.
  25. PanSci: Offshore Wind Turbine Construction Expensive and Troublesome, Why Taiwan Still Develops Heavily — Content Curation Partner per MOU 2026-05-05. Taiwan Strait due to topographical factors forms "pipe effect," causing wind speeds in strait much higher than surrounding waters, making Taiwan one of most potential offshore wind development locations globally.
  26. PV Magazine: Taiwan solar and offshore wind targets — Reporting Ørsted completed construction of 920MW for Da Changhua Southwest Phase II and Northwest Wind Farms, and Taiwan's plan to add 8.2GW of solar PV and offshore wind by the end of 2026.
  27. Environmental Information Center: Changhua Fishermen Protest Offshore Wind (2022) — Reporting over a hundred fishermen going to the Executive Yuan to protest offshore wind farm navigation ban zones blocking generational operation sea areas, shouting "Eliminate Fishermen" slogan.
  28. Environmental Information Center: Court Rules Offshore Wind Navigation Restrictions Illegal (2025) — Taiwan's first court challenge to offshore wind spatial governance ruling, determining navigation restrictions infringe on fishermen's rights, causing shock in the energy circle.
  29. Taipower: Renewable Energy Power Generation Statistics — Taiwan Power Company official statistics, recording annual data of various renewable energy installed capacity and power generation; 2024 solar PV installed capacity 14,281 MW, power generation 14.9 billion kWh.
  30. Taipower: 513 Blackout Accident Preliminary Investigation Out — ; Ministry of Economic Affairs: 513 and 517 Blackout Accident Review Report — Official data explains the accidental operation of switch 3541 in the 513 accident, causing an instantaneous reduction of about 2.2GW in power supply capacity and affecting about 4 million households, and organizing the 517 event and subsequent review.
  31. Presidential Office Press Release: Taiwan Carbon Exchange Unveiling — ; Taiwan Stock Exchange 2023 Annual Report — Carbon Exchange unveiled on August 7, 2023; planned capital 1.5 billion NTD, initial paid-in capital 1 billion NTD, Stock Exchange contributed 600 million NTD, National Development Fund contributed 400 million NTD. Stock Exchange annual report also states the first batch of international carbon credit transactions totaled 88,520 tons CO2e, participating enterprises 27 (including 45 with financial holding subsidiaries).
  32. KPMG Taiwan: Carbon Pricing Trend Analysis (2025) — Analyzing market dynamics after Taiwan's carbon fee system went online in 2025, including domestic carbon pricing (Formosa 3,000 NTD/ton, Hanbao Agriculture 3,000-4,000 NTD/ton) and the challenge of low trading volume.
  33. EU Carbon Border Adjustment Mechanism Official Page — CBAM entered the transition period in October 2023, fully implemented in 2026, covering six major product categories: steel, cement, aluminum, fertilizers, electricity, and hydrogen.
  34. Reccessary: Taiwan Energy Policy 2025 Outlook — Reporting Lai Ching-te's 2024 National Day Speech announced "Secondary Energy Transition" policy direction: diversified green energy, deep energy saving, advanced energy storage.
  35. Ministry of Economic Affairs Energy Bureau Statistics: Power Generation Structure - By Fuel Type — ; Ministry of Environment Energy Information Platform: Power Structure — ; Economic Daily: Ministry of Economic Affairs Says Renewable Energy Share Can Reach 20% from November 2026 — According to Ministry of Economic Affairs Energy Bureau statistics, 2024 gas about 42.4%, coal about 39.3%, renewables about 11.5% to 11.6%, nuclear about 4.2%; Ministry of Environment Energy Information Platform shows renewables share in national total power generation in 2025 is 13.1%, while Taipower system purchase-sell structure chart common口径 is about 12.7%, two different口径. Ministry of Economic Affairs stated in May 2025, estimated to reach 20% from November 2026, about 30% by 2030.
  36. Presidential Office Press Release: Tsai Ing-wen 2021 Earth Day Talk — Tsai Ing-wen first declared as President that "2050 Net-Zero Transition is the goal of the world, and also Taiwan's goal," laying the policy tone for the subsequent NDF Net-Zero Roadmap.
  37. United Daily News Vision Project: Hsu Hsiung-hsiung Interview — Academia Sinica Center for Environmental Change Research Distinguished Researcher Hsu Hsiung-hsiung's team analyzed Taiwan's temperature data from 1911-2020, pointing out Taiwan's century-long warming of 1.6°C, winter shortened by nearly half, worst-case scenario winter days may drop to zero after 2060.
  38. CSRone Sustainable Think Tank: Wang Chung-ho Interview — Academia Sinica Institute of Earth Sciences Adjunct Researcher Wang Chung-ho has long tracked Taiwan's sea-level changes, pointing out the rate of sea-level rise around Taiwan is higher than the global average; the article uses a more conservative risk description to avoid simplifying different research scenarios into absolute conclusions.
  39. Central Weather Bureau Climate Change Information Platform — Taiwan climate observation historical database, recording century-long temperature, rainfall, extreme weather event records of each station, including the increasing trend of days above 35°C in Taipei.
  40. BBC Chinese: Taiwan's 56-Year Worst Drought (2021) — Reporting on the 2021 severe drought in central and southern Taiwan, reservoir storage rates dropped below 10%, tech factories like TSMC activated water truck emergency measures.
  41. National Center for Disaster Prevention and Rescue Technology Center: Morakot Typhoon Disaster Record — Official disaster archive, recording Morakot Typhoon Alishan station cumulative rainfall of 2,884 mm, the highest record in Taiwan's meteorological observation history.
  42. The Reporter: Hsiao-lin Village Extinction Investigation — In-depth investigation into the process of Hsiao-lin Village Xiandu Mountain collapse and the complete context of 491 deaths, including geological causes and early warning system failure analysis.
  43. Environmental Information Center: 2024 National Climate Change Science Report — Reporting key findings of the latest scientific report hosted by Hsu Hsiung-hsiung: 50-year extreme rainfall may become 10-year, days above 36°C may increase by 75 days.
  44. Ministry of Environment Greenhouse Gas Emission Statistics — Taiwan official greenhouse gas emission database, recording national emission inventories, sectoral emissions, and per capita emission data over the years.
Sobre este artículo Este artículo fue creado mediante colaboración comunitaria y asistencia de IA.
climate change net-zero transition energy transition Nuclear Three nuclear waste hydrogen energy geothermal ocean energy offshore wind solar PV carbon credit trading Lanyu extreme climate
Compartir